三年前考了CPIM-Part1,當(dāng)時(shí)基于IMM教材框架寫了一份摘要筆記,分享在這里。
其實(shí)IMM此書幾乎囊括了供應(yīng)鏈管理從計(jì)劃釋放到尋源、制造、物流運(yùn)輸、倉儲(chǔ)環(huán)節(jié)的各個(gè)方面,對(duì)于不打算考取CPIM證書,只是想對(duì)于供應(yīng)鏈管理有一個(gè)初步的知識(shí)體系搭建也很有益處,希望此分享對(duì)供應(yīng)鏈友人們有所幫助,也期待和大家互動(dòng)交流。
因復(fù)習(xí)時(shí)使用的IMM教材英文版,筆記同為英文版,偶爾穿插中文注釋,及相對(duì)原教材的摘取刪減。
Note: S&OP focusnot on actual schedule production, but producing a high-level plan for the useof company resources, including production resources, human resources, salesresources, financial resources and all other functions in company.
Purpose of production plan: establish production rates that will accomplish the objectives of the strategic businessplan.
Making production plan
1) establish production groups
->based on thesimilarity of manufacturing process
->the demand forgood translate into the demand for capacity.
2)basic strategies
->chases trategy: demand matching strategy
->production leveling
->subcontracting
->hybrid strategy(組合)
3)operation environment
3.1)Make to stock production plan
->目標(biāo):maintain required inventory levels
3.2)make to order production plan /assemble to order
->目標(biāo):maintain the planned backlog
4)Resource planning
->生產(chǎn)計(jì)劃做完后,must be compared to the exsitingresources
->resourcebill
Objectives: to balance the demand (priorities)set by the market plan with the availability of materials, labor and equipment(capacity) of manufacturing.
MPS isthe planned build schedule for manufacturing.
Relationship to production plans
->基于prodcution plan 的forecast, projected available, openinventory(初始庫存) and strategy
(書中使用表格計(jì)算轉(zhuǎn)換productionplan為MPS的過程邏輯)
3 steps to develop a master production schedule
->1. a preliminary MPS 初始主排程計(jì)劃
->2.RCCP:
Check whether critical resources(包括bottleneck resources, labor, critical materials) are available for step (1) MPS.
使用resource bill(單位產(chǎn)品的產(chǎn)能需求)與MPS矩陣相乘,可以得到RRCP
->3.resolve diff between 1 & 2
Resource use
Customer service(due date滿足交貨期否?)
Cost
Master schedule decisions
->take place where the smallest number of product options exist.
Production planning, master scheduling and sales
->production plan(產(chǎn)品族級(jí)別) provide framework for MPS(End items)
What production can and will do
MPS & Delivery promises
ATP forperiod 1= on hand inventory - customer orders due before next MPS
ATP forperiod 2=MPS scheduled receipt - customer orders due before next MPS
->Note: 這種計(jì)算方法假設(shè)the ATP will be sold before the next scheduled receipt arrives.
Before the demand time fence
PAB=prior period PAB or on-hand balance + MPS - customer orders
After the demand time fence
PAB=prior period PAB + MPS - max{customer order, forecast}
Objectives: determine requirements & keeppriorities current
Input:
->MPS
->Inventory records: planning factors & inventory record file
->BOM:
多種形式,eg. Multiple level, single level, planning bill
Where-used report(cs15 T-Code) & pegging report (有需求對(duì)應(yīng)的cs15)
Usage
MRP Process basic techniques
->Exploding and offsetting
Planned order receipt
Planned order release = planned order receipt* (1 - scrap factor)
->Gross and net requirements
Net = Gross - available inventory
The planned order release of the parent becomes the gross requirements of the component
->Releasing orders
Scheduled receipts: when the authorization to purchase or manufacture is released, the planned order receipt is cancelled, a scheduled receipt is created in its place
Net= gross- scheduled receipts - available inventory
->Capacityrequirements planning
->Low-levelcoding and netting
Use MRP
Material planners work with 3 types of orders
Planned orders
Released orders
Firm planned orders
Managing MRP
Priority
Bottom-up replaning: actions to correct for changed conditions should occur as low in theproduct structure as possible
Reducing system nervousness: one method is firm planned orders
Capacityis a rate of doing work, not the qty.
Capacity required(load)
Capacity management
Capacity planning
Capacity control
Capacity requirements planning
->inputs:
Open order file
Material requirements plan
Routing file
Workcenter file
Shop calendar: eg. Move time/wait time/ queue time/ lead time
Capacity available
->affected by
Product specifications
Product mix
Plant and equipment
Work effort
->measuring capacity
If 產(chǎn)品種類少:a unit common to all products
If 產(chǎn)品種類多:standard time
->two methods to check capacity available
1)measurements: demonstrated (measured ) capacity from historical data, is averate, not max, output. = sum of standard hours per time bucket/ number of time buckets
2)calculated or rated capacity = (available time) * (utilization) * (efficiency)
Capacity required (load)
Determine the time needed for each order at each work center.
Obtain load from summing up the capacity required for individual orders
Scheduling orders
->backscheduling
需要的信息:queue, wait, move time, workcenter capa., qty, due date, operation sequence, setup, run time.
信息來源:order file, route file, work center file
Process
Making the plan
負(fù)荷與可用產(chǎn)能不同時(shí),可采取的措施
Eg.Overtime/ shift + & -/ alternate routings/ subcontract…
Manufacturing systems
->flow manufacturing: (Repetitive manufacturing /Continuous manufacturing)
Routing fixed
Work center produce a limited range of similar products
WIP little, throughput times low
Capacity is fixed by line
->intermittent manufacturing
Work flow not balanced
Work centers are usually grouped according to function
WIP large, throughput times long
Capacity difficult to predict
->project manufacturing, (eg, shipbuilding)
Data requirements
->planning files
Item master file 物料主數(shù)據(jù)
Product structure file (BOM file)
Routing file
Workcenter master file
->control files
Shop order master file
Shop order detail file
Order preparation
Check material availability & capacity availability
Scheduling techniques
Forward Scheduling : decide the earliest delivery date
Backward scheduling: determine when an order must be started
Infinite loading & finite loading
Operation overlapping 重疊
MLT(manufacturing lead time)is reduced by the overlap time and the elimination of queue time.
Costs involved: move cost; increase queue time of other orders
重點(diǎn): operation time B shorter than operation time A =>confirm sublot
Operation splitting 拆分
MLT is reduced by several lots running on two + machines
重點(diǎn): setup is low; a suitable workcenter is idle; one operator run several machines
Load leveling
Scheduling bottlenecks
Throughput
Some bottleneck principles
Manage bottlenecks
Time buffer before bottleneck
Control rate of material feeding the bottleneck
Provide the needed bottleneck capacity (eg. 減少準(zhǔn)備時(shí)間等等)
Adjust load (eg.改工作中心,外包),強(qiáng)調(diào) reduce load
Change schedule
Theory of constraints & drum-buffer-rope
-manage the constraint
-improve the process
-scheduling with the theory of constraints
Drum: pace of production
Buffer: a time buffer established in front of the constraint
Rope: pull production to the constraint for necessary processing
-control: queue time 占比最大,是重點(diǎn)控制方向
Input/output control
Priority setting
-Priority:operation sequencing
Control of priorities is exercised through dispatching
Dispatching rules
FCFS
EDD(ealiest job due date)
ODD(ealiest operation due date)
SPT(shortest process time)
CR(Critical ratio) = (due date - present date)/ lead time remaining
CR<1, behind schedule
CR=1, on schedule
CR>1, ahead of schedule
CR<=0, already late
Introduction
->purchasing objectives
The required qyt. & quality
The lowest cost
Service and delivery
Good supplier relations & developing potential suppliers
Minimize the impact on the environment
->outsourcing
->purchasing cycle
Receiving and analyzing PR
Selecting suppliers
Requesting quotations
Determining the right price
Issuing purchase order
Following up & delivery
Receiving and accepting goods
Approving invoice
Establishing specifications
Qty. requirement
Price requirement
Functional requirements: functional specifications & quality ; value analysis
Functional specification description
By brand: usually have price levels higher than non-branded items
By specification: physical and chemical characteristics/ material and method of manufacture/ performance
By engineering drawings
Miscellaneous
Selecting suppliers
->sourcing: sole/multiple/ single
->factors:technical ability/ manufacturing capa/ reliability/ after-sales service/location/ JIT capabilities/ price/ other
->identifying
->finalselection: ranking method
Price determination
->basis for pricing: fixed cost, variable cost
->competitive bidding競(jìng)價(jià)
->price negotiation
Impact of MRP on purchasing
->purchasing可分為2種類型的行為:
1)procurement
2)supplier scheduling & follow-up
->planner/buyerconcept
->contract buying: 供應(yīng)商得到 a copy ofMR to confirm furture demands
->supplier responsiveness & reliability
->close relationship with suppliers
->EDI
->VMI
->internet& intranet & extranet
Environmentally responsible purchasing
->reduce-reuse-recycle
Expansion of purchasing into supply chain management
->信息流, 現(xiàn)金流, 物料流, 維修流
->CRM& SRM
Demand management 4 main activities
->forecasting
->order processing
->making delivery promises
->interfacing between manufacturing planning & control & market
Characteristics of demand
->demand patterns
Trend
Seasonality
Random variation
Cycle
->stable vs dynamic
->dependent vs independent demand
Principles of forecasting
->wrong
->includean estimate of error
->more accurate for families/ groups
->more accurate for nearer time periods
Collection & preparation of data
->record data in same terms as needed for forecast
->record the circumstances
->record the demand separately for different customer groups
Forecasting techniques
->qualitative techniques: eg. Business trends/ potential demand, senior management
->extrinsic techniques
->intrinsic techniques (end-item)
Some intrinsic techniques
->moving average: 優(yōu)點(diǎn):stabledemand, filter out random fluctuations, 缺點(diǎn):computerstorage high
->exponential smoothing: 優(yōu)點(diǎn):deal withstable item, short-range forecast,缺點(diǎn):not work well when demand, low, intermitent
Seasonality
->seasonal demand = (seasonal index) * (average demand)
->deseasonalized demand = (actual seasonal demand) / seasonal index
->計(jì)算步驟:
Use de-seasonalized data to forecast
Calculate desonalized demand base forecast
Calculate seasonal forecast using seasonal index
Tracking forecast
->error
Bias & random variation
->MAD(Mean Absolute Deviation)
->tracking signal = forecast error代數(shù)和/MAD; 作用:measure the quality of forecast todetermine whether to adjust forecast
->contingency planning
->P/DRatio
->Aggregate inventory management: according to classification & cuntion
->Item inventory management: eg. ABC/EOQ, order system
Inventory & material flow
->R.M/WIP/ Finished goods/Distribution inventories/ MROs(Maintenance, Repair,Operational Supplies)
Functions of inventories
->anticipation inventory: level production & reduce cost of changing production rates
->fluctuation inventory: (safety stock)
->lot-size inventory(cycle stock): quantity discounts; to reduce shipping, setup costs
->transportation inventory(pipeline/ movement inventories)在途庫存
->MROs
Objectives
->maximum customer services by protecting against uncertainty
->min inventory investment
->operating efficiency
Build up inventories between different rates of production
Level production and build anticipation inventory for seasonal products
Allow manufacturing to run longer production runs
Allow manufacturing to purchase in larger qty.
Inventory cost
->item cost
->carrying cost (capital cost/ storage cost/ risk cost)
->ordering cost
->stockout cost
->capacity-associatedcost (eg. Overtime, hiring, extra shifts)
Financial statement and inventory
->balance sheet: Assets = liabilities + owner's equity
->income statement: Income = revenue - expenses
->cash flow analysis: show company's ability to pay off debt
->financial inventory performance measures
->methods of evaluating inventory (FIFO/LIFO/Average cost/Standard cost)
lot-size decision rules
lot forlot/ fixed-order qty.(EOQ)/ order n periods supply(POQ)
3種系統(tǒng)to determine when to order
Order point system (OP= DDLT +SS) DDLT: Demand during lead time; SS: safety stock
Periodic review system
MRP
Determining service level
->is adecision of senior management & company's cooperate and marketing strategy
Warehouse management
->objectives
->cost:capital cost & operating cost
->warehouse activities
->maxuse of space & effective use of labor and equipment
Cube utilization & accessibility
Stock location
Order picking & assembly
Physical control & security
Inventory record accuracy
Introduction
->channels of distribution
Transaction channel: the transfer of ownership
Distribution channel: the transfer or delivery of goods/services
->reverse logistics
Purpose: return, repair, remanufacture, recycling
Two main categories: asset recovery: actual products; green reverse logistics: package/ heavy metal
Physical distribution system
->activities/total-costconcept/ global distribution/3PL
Interfaces
->marketing(responsible for transferring ownership) & production
Transportation
Legal Types of carriage
Transportation cost elements
->line-haul costs(LHC)
->Pickup and delivery costs
->terminal handling
->billing & collecting
->transportation terms, incoterms
warehousing
->roleof warehouses: transportation consolidation/ product mixing/ service
Continuous improvements of products & processes
->ensuring employee involvement & empowerment
->focusing on customers as the ultimate definer of quality
->sustainability continuous improvement -> ongoing cycle
Lean tools & techniques
->Hoshin planning: use PDCA cycle
->Kaizen events
->valuestream mapping
->Poka-yoke
->5S
TQM & other quality tools
->quality principal approaches: transcendent quality/ product-based quality/ user-basedquality/ manufacturing-based quality/ value-based quality
->some quality tools
Check sheets/ pareto charts/ cause and effect diagrams/ flowcharts/ histograms/ statistical process control/ scatter diagrams
京東完成對(duì)達(dá)達(dá)集團(tuán)的私有化收購,達(dá)達(dá)將從美股退市
1290 閱讀京東物流江西省大件京東幫招商
1198 閱讀瑪氏中國|2025年度冠軍寵物進(jìn)口貨運(yùn)代理服務(wù)遴選
1137 閱讀順新暉和寧德時(shí)代簽署戰(zhàn)略合作協(xié)議,共建“零碳冷鏈”生態(tài)圈
1141 閱讀京東物流陜西省大件京東幫招商
1109 閱讀知名網(wǎng)絡(luò)貨運(yùn)平臺(tái)去年?duì)I收397.97億,凈利潤實(shí)現(xiàn)1.4億元
991 閱讀菜鳥與全球糖果巨頭不凡帝范梅勒達(dá)成供應(yīng)鏈合作
909 閱讀菜鳥在加拿大加開海外倉,加速全球供應(yīng)鏈倉網(wǎng)建設(shè)
925 閱讀飛熊領(lǐng)鮮C輪融資落地,進(jìn)口凍品產(chǎn)業(yè)互聯(lián)網(wǎng)平臺(tái)加速全鏈路生態(tài)布局
928 閱讀《2024年交通運(yùn)輸行業(yè)發(fā)展統(tǒng)計(jì)公報(bào)》發(fā)布
846 閱讀